Recommended assembly method

1. Install at ambient temperatures above 10° C (preferably between 15 and 25° C)
  


2. Surfaces should be clean and dry, free of
      dust, grease, oil and any other loose matter


3. Remove the protective release paper
     taking care not to touch the adhesive

4. Place the hanger in the required position
and press the base against the surface to be insulated
  
                               
5. Insulation can be impaled immediately and firmly locked with fastening clips
but maximum strength of adherence is achieved after 24 hours
  

6. If necessary, cover the pin with a
   protective nylon cap NSC-27
      
Back to "Self adhesive hangers SC"     Quantity and positioning of hangers    Sales program